Assessment Year | 1986 |
---|---|
Principal Product | ALUMINUM BUMPERS |
NAICS |
n/a
|
SIC | 3471: Electroplating, Plating, Polishing, Anodizing, and Coloring |
Sales Range | $50 M to 100M |
# of Employees | 120 |
Plant Area |
n/a
|
Annual Production | 1,200,000
pieces
|
Production Hrs. Annual | 4,200
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $517,000 | 9,242,087 |
kWh
|
$0.056 |
Natural Gas | $460,300 | 88,050 |
MMBtu
|
$5.23 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $124,210 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $112,192 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $50,976 | - |
$50,976
-
kWh
|
- | - | |
02 | 2.4322: Use or replace with energy efficient substitutes | $12,018 | $6,000 |
$12,018
199,590
kWh
|
- | - | |
03 | 2.2414: Use waste heat from hot flue gases to preheat | $28,028 | $25,000 | - |
$28,028
-
MMBtu
|
- | |
04 | 2.2414: Use waste heat from hot flue gases to preheat | $26,250 | $27,000 | - |
$26,250
-
MMBtu
|
- | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $6,938 | $16,000 |
$7,845
133,939
kWh
|
$(-1,332.0)
-
MMBtu
|
$425 | |
TOTAL RECOMMENDED | $124,210 | $74,000 |
$70,839
333,529
kWh
|
$52,946
-
MMBtu
|
$425 | ||
TOTAL IMPLEMENTED | $112,192 | $68,000 |
$58,821
133,939
kWh
|
$52,946
-
MMBtu
|
$425 |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs