| Assessment Year | 1986 |
|---|---|
| Principal Product | BALL BEARING ASSEMBLIES |
| NAICS |
n/a
|
| SIC | 3462: Iron and Steel Forgings |
| Sales Range | $10 M to 50M |
| # of Employees | 130 |
| Plant Area |
n/a
|
| Annual Production | 24,000,000
pieces
|
| Production Hrs. Annual | 4,500
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $247,807 | 3,240,914 |
kWh
|
$0.076 |
| Natural Gas | $36,913 | 7,757 |
MMBtu
|
$4.76 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $34,032 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $30,530 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7111: Reduce illumination to minimum necessary levels | $19,049 | $5,470 |
$18,408
279,308
kWh
|
- | $641 | |
| 02 | 2.2437: Recover waste heat from equipment | $3,039 | $9,500 | - |
$3,039
-
MMBtu
|
- | |
| 03 | 2.6218: Turn off equipment when not in use | $463 | $129 |
$119
2,638
kWh
|
$344
-
MMBtu
|
- | |
| 04 | 2.3191: Use demand controller or load shedder | $11,481 | - |
$5,865
-
kWh
|
$5,616
-
MMBtu
|
- | |
| TOTAL RECOMMENDED | $34,032 | $15,099 |
$24,392
281,946
kWh
|
$8,999
-
MMBtu
|
$641 | ||
| TOTAL IMPLEMENTED | $30,530 | $5,470 |
$24,273
279,308
kWh
|
$5,616
-
MMBtu
|
$641 | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs