ITAC Assessment: UD0188
ITAC logo
ITAC Assessment: UD0188
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1986
Principal Product FABR. STRUCTURAL STEEL
NAICS
n/a
SIC 3441: Fabricated Structural Metal
Sales Range $5
M
to 10
M
# of Employees 45
Plant Area
n/a
Annual Production 0
units
Production Hrs. Annual 2,250
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $48,764 472,157
kWh
Natural Gas $15,558 2,450
MMBtu
Fuel Oil #2 $6,218 1,065
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $5,412 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $4,133

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $4,133 $13,400 $4,687
45,428
kWh
$(-554.0)
-
MMBtu
02 2.3131: Reschedule plant operations or reduce load to avoid peaks $1,279 - $1,279
-
kWh
-
TOTAL RECOMMENDED $5,412 $13,400 $5,966
45,428
kWh
$(-554.0)
-
MMBtu
TOTAL IMPLEMENTED $4,133 $13,400 $4,687
45,428
kWh
$(-554.0)
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs