| Assessment Year | 1985 |
|---|---|
| Principal Product | TANKS & PROCESS EQUIPMENT |
| NAICS |
n/a
|
| SIC | 3443: Fabricated Plate Work (Boiler Shops) |
| Sales Range | $10 M to 50M |
| # of Employees | 230 |
| Plant Area |
n/a
|
| Annual Production | 0
units
|
| Production Hrs. Annual | 6,120
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $118,839 | 1,477,140 |
kWh
|
$0.080 |
| Natural Gas | $63,139 | 11,667 |
MMBtu
|
$5.41 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $25,286 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $25,286 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings |
|---|---|---|---|---|---|
| 01 | 2.7492: Use proper thickness of insulation on building envelope | $25,286 | $48,000 |
$25,286
737,397
kWh
|
|
| TOTAL RECOMMENDED | $25,286 | $48,000 |
$25,286
737,397
kWh
|
||
| TOTAL IMPLEMENTED | $25,286 | $48,000 |
$25,286
737,397
kWh
|
||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs