Assessment Year | 1985 |
---|---|
Principal Product | AIR CYLINDERS & VALVES |
NAICS |
n/a
|
SIC | 3443: Fabricated Plate Work (Boiler Shops) |
Sales Range | $5 M to 10M |
# of Employees | 110 |
Plant Area |
n/a
|
Annual Production | 0
units
|
Production Hrs. Annual | 4,300
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $91,651 | 1,372,216 |
kWh
|
$0.067 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $4,169 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $4,169 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings |
---|---|---|---|---|---|
01 | 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary | $1,203 | $150 |
$1,203
39,566
kWh
|
|
02 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $1,225 | $50 |
$1,225
-
kWh
|
|
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,195 | $123 |
$1,195
19,637
kWh
|
|
04 | 2.6121: Reduce hot water temperature to the minimum required | $546 | - |
$546
8,206
kWh
|
|
TOTAL RECOMMENDED | $4,169 | $323 |
$4,169
67,409
kWh
|
||
TOTAL IMPLEMENTED | $4,169 | $323 |
$4,169
67,409
kWh
|
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs