ITAC Assessment: UD0169
ITAC logo
ITAC Assessment: UD0169
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1985
Principal Product SPECIAL MACHINES FOR INDUSTRY
NAICS
n/a
SIC 3544: Special Dies and Tools, Die Sets, Jigs and Fixtures, and Industrial Molds
Sales Range $10
M
to 50
M
# of Employees 175
Plant Area
n/a
Annual Production 0
units
Production Hrs. Annual 6,760
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $70,379 1,174,385
kWh
Natural Gas $22,252 3,880
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $5,129 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $2,164

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.7494: Install storm windows and doors $2,965 $3,680 - $2,965
-
MMBtu
02 2.7142: Utilize higher efficiency lamps and/or ballasts $1,315 $178 $1,672
27,550
kWh
$(-357.0)
-
MMBtu
03 2.6121: Reduce hot water temperature to the minimum required $849 - $681
11,137
kWh
$168
-
MMBtu
TOTAL RECOMMENDED $5,129 $3,858 $2,353
38,687
kWh
$2,776
-
MMBtu
TOTAL IMPLEMENTED $2,164 $178 $2,353
38,687
kWh
$(-189.0)
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs