ITAC Assessment: SD0557
ITAC logo
ITAC Assessment: SD0557
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2017
Principal Product Hard disk drive components
NAICS 334112: Computer Storage Device Manufacturing
SIC 3572: Computer Storage Devices
Sales Range $10
M
to 50
M
# of Employees 75
Plant Area 27,000
ft2
Annual Production 70,000,000
units
Production Hrs. Annual 3,900
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $190,051 1,110,806
kWh
Natural Gas $3,802 3,213
MMBtu
TOTAL YEARLY COSTS $193,853
RECOMMENDED SAVINGS* $64,008 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $6,518

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Ancillary Material Cost Savings
01 2.1311: Replace electrically-operated equipment with fossil fuel equipment $43,867 $5,775 $53,735
314,053
kWh
$(-9,868.0)
-
MMBtu
-
02 2.7142: Utilize higher efficiency lamps and/or ballasts $7,848 $25,956 $7,631
44,595
kWh
- $217
03 2.4133: Use most efficient type of electric motors $3,188 $9,450 $3,188
18,634
kWh
- -
04 2.4239: Eliminate or reduce compressed air usage $2,587 $3,500 $2,587
15,120
kWh
- -
05 2.4231: Reduce the pressure of compressed air to the minimum required $2,478 $600 $2,478
14,483
kWh
- -
06 2.7135: Install occupancy sensors $1,570 $1,860 $1,570
9,179
kWh
- -
07 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,245 $900 $1,245
7,274
kWh
- -
08 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $1,225 $3,775 $1,225
7,160
kWh
- -
TOTAL RECOMMENDED $64,008 $51,816 $73,659
430,498
kWh
$(-9,868.0)
-
MMBtu
$217
TOTAL IMPLEMENTED $6,518 $7,135 $6,518
38,096
kWh
- -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs