ITAC Assessment: UD0164
ITAC logo
ITAC Assessment: UD0164
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1985
Principal Product CORRUGATED BOXES
NAICS
n/a
SIC 2653: Corrugated and Solid Fiber Boxes
Sales Range $1
M
to 5
M
# of Employees 56
Plant Area
n/a
Annual Production 60,000
thousand feet
Production Hrs. Annual 2,080
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $35,043 592,907
kWh
Natural Gas $60,548 11,899
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $18,637 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $14,637

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.5123: Reduce fluid flow rates $513 $150 $396
7,620
kWh
$117
-
MMBtu
02 2.7494: Install storm windows and doors $1,368 $1,226 - $1,368
-
MMBtu
03 2.2414: Use waste heat from hot flue gases to preheat $12,756 $25,000 - $12,756
-
MMBtu
04 2.2437: Recover waste heat from equipment $4,000 $13,000 - $4,000
-
MMBtu
TOTAL RECOMMENDED $18,637 $39,376 $396
7,620
kWh
$18,241
-
MMBtu
TOTAL IMPLEMENTED $14,637 $26,376 $396
7,620
kWh
$14,241
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs