ITAC Assessment: UD0151
ITAC logo
ITAC Assessment: UD0151
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1985
Principal Product MOLDED PLASTIC PARTS
NAICS
n/a
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $1
M
to 5
M
# of Employees 47
Plant Area
n/a
Annual Production 0
units
Production Hrs. Annual 6,240
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $63,541 1,058,324
kWh
Natural Gas $835 142
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $2,306 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $1,349

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.6222: Use drying oven (batch type) on alternate days or other optimum schedule to run equipment with full loads $162 - $162
5,569
kWh
- -
02 2.2511: Insulate bare equipment $1,349 $315 $1,349
22,567
kWh
- -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $795 $284 $797
15,826
kWh
$(-62.0)
-
MMBtu
$60
TOTAL RECOMMENDED $2,306 $599 $2,308
43,962
kWh
$(-62.0)
-
MMBtu
$60
TOTAL IMPLEMENTED $1,349 $315 $1,349
22,567
kWh
- -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs