| Assessment Year | 1984 |
|---|---|
| Principal Product | UNIFORMS |
| NAICS |
n/a
|
| SIC | 2326: Men's and Boys' Work Clothing |
| Sales Range | $10 M to 50M |
| # of Employees | 193 |
| Plant Area |
n/a
|
| Annual Production | 0
units
|
| Production Hrs. Annual | 2,275
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $69,670 | 919,988 |
kWh
|
$0.076 |
| Natural Gas | $31,235 | 5,315 |
MMBtu
|
$5.88 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $5,111 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $5,111 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.4322: Use or replace with energy efficient substitutes | $2,095 | $1,000 | - |
$2,095
-
MMBtu
|
|
| 02 | 2.7122: Disconnect ballasts | $1,386 | $2,310 |
$1,562
21,102
kWh
|
$(-176.0)
-
MMBtu
|
|
| 03 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $1,630 | - |
$1,630
-
kWh
|
- | |
| TOTAL RECOMMENDED | $5,111 | $3,310 |
$3,192
21,102
kWh
|
$1,919
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $5,111 | $3,310 |
$3,192
21,102
kWh
|
$1,919
-
MMBtu
|
||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs