ITAC Assessment: UD0120
ITAC logo
ITAC Assessment: UD0120
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1984
Principal Product TIRE PROCESSING,STORAGE
NAICS
n/a
SIC 3011: Tires and Inner Tubes
Sales Range $10
M
to 50
M
# of Employees 70
Plant Area
n/a
Annual Production 0
units
Production Hrs. Annual 5,017
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $146,253 2,982,708
kWh
Natural Gas $53,128 9,109
MMBtu
Fuel Oil #2 $2,700 420
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $26,558 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $26,558

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $26,558 $83,000 $27,192
590,270
kWh
$(-634.0)
-
MMBtu
TOTAL RECOMMENDED $26,558 $83,000 $27,192
590,270
kWh
$(-634.0)
-
MMBtu
TOTAL IMPLEMENTED $26,558 $83,000 $27,192
590,270
kWh
$(-634.0)
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs