ITAC Assessment: UD0110
ITAC logo
ITAC Assessment: UD0110
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1983
Principal Product BREADS, DANISH, BUNS
NAICS
n/a
SIC 2051: Bread and Other Bakery Products, Except Cookies and Crackers
Sales Range $5
M
to 10
M
# of Employees 125
Plant Area
n/a
Annual Production 0
units
Production Hrs. Annual 3,276
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $98,826 1,788,980
kWh
Natural Gas $187,566 34,097
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $35,526 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
02 2.7492: Use proper thickness of insulation on building envelope $18,169 $48,000 - $18,169
-
MMBtu
03 2.1233: Analyze flue gas for proper air/fuel ratio $933 - - $933
-
MMBtu
04 2.7142: Utilize higher efficiency lamps and/or ballasts $2,620 $682 $3,228
72,392
kWh
$(-608.0)
-
MMBtu
05 2.2414: Use waste heat from hot flue gases to preheat $13,804 $30,000 - $13,804
-
MMBtu
TOTAL RECOMMENDED $35,526 $78,682 $3,228
72,392
kWh
$32,298
-
MMBtu
TOTAL IMPLEMENTED - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs