| Assessment Year | 1983 |
|---|---|
| Principal Product | TOOLS,DIES,SPECIAL MACHINE PARTS |
| NAICS |
n/a
|
| SIC | 3544: Special Dies and Tools, Die Sets, Jigs and Fixtures, and Industrial Molds |
| Sales Range | $5 M to 10M |
| # of Employees | 99 |
| Plant Area |
n/a
|
| Annual Production | 0
units
|
| Production Hrs. Annual | 4,680
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $28,165 | 408,558 |
kWh
|
$0.069 |
| Other Energy | $26,586 | 2,703 |
MMBtu
|
$9.84 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $16,671 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $13,125 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Other Energy Savings |
|---|---|---|---|---|---|---|
| 01 | 2.7492: Use proper thickness of insulation on building envelope | $9,144 | $18,000 | - |
$9,144
-
MMBtu
|
|
| 02 | 2.1391: Replace purchased steam with electric heating | $3,546 | $2,000 |
$(-506.0)
(-6,448)
kWh
|
$4,052
-
MMBtu
|
|
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $583 | $172 |
$793
9,379
kWh
|
$(-210.0)
-
MMBtu
|
|
| 04 | 2.7494: Install storm windows and doors | $3,398 | $2,560 | - |
$3,398
-
MMBtu
|
|
| TOTAL RECOMMENDED | $16,671 | $22,732 |
$287
2,931
kWh
|
$16,384
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $13,125 | $20,732 |
$793
9,379
kWh
|
$12,332
-
MMBtu
|
||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs