ITAC Assessment: UD0082
ITAC logo
ITAC Assessment: UD0082
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1983
Principal Product CHROME PLATED PLASTIC
NAICS
n/a
SIC 3471: Electroplating, Plating, Polishing, Anodizing, and Coloring
Sales Range $1
M
to 5
M
# of Employees 112
Plant Area
n/a
Annual Production 0
units
Production Hrs. Annual 6,700
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $68,998 1,348,183
kWh
Natural Gas $27,161 5,906
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $6,723 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $820 $206 $1,024
21,102
kWh
$(-204.0)
-
MMBtu
-
02 2.6121: Reduce hot water temperature to the minimum required $170 - $170
3,224
kWh
- -
03 2.2511: Insulate bare equipment $922 $1,200 $1,176
24,912
kWh
$(-254.0)
-
MMBtu
-
04 2.2444: Use hot process fluids to preheat incoming process fluids $4,811 - $(-221.0)
(-4,396)
kWh
$2,206
-
MMBtu
$2,826
TOTAL RECOMMENDED $6,723 $1,406 $2,149
44,842
kWh
$1,748
-
MMBtu
$2,826
TOTAL IMPLEMENTED - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs