ITAC Assessment: UD0078
ITAC logo
ITAC Assessment: UD0078
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1983
Principal Product CORRUGATED CONTAINERS
NAICS
n/a
SIC 2653: Corrugated and Solid Fiber Boxes
Sales Range $10
M
to 50
M
# of Employees 120
Plant Area
n/a
Annual Production 0
units
Production Hrs. Annual 6,000
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $72,804 1,442,849
kWh
Natural Gas $151,067 32,113
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $33,400 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $3,461 $238 $4,229
84,701
kWh
$(-768.0)
-
MMBtu
02 2.1221: Replace obsolete burners with more efficient ones $16,479 $50,000 - $16,479
-
MMBtu
03 2.2443: Re-use or recycle hot or cold process exhaust air $13,460 $33,725 - $13,460
-
MMBtu
TOTAL RECOMMENDED $33,400 $83,963 $4,229
84,701
kWh
$29,171
-
MMBtu
TOTAL IMPLEMENTED - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs