ITAC Assessment: UD0075
ITAC logo
ITAC Assessment: UD0075
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1983
Principal Product COMMERCIAL PRINTINGS
NAICS
n/a
SIC 2752: Commercial Printing, Lithographic
Sales Range $10
M
to 50
M
# of Employees 260
Plant Area
n/a
Annual Production 0
units
Production Hrs. Annual 6,800
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $256,812 5,607,855
kWh
Natural Gas $58,574 13,675
MMBtu
Other Energy $75,605 8,267
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $62,548 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Other Energy Savings Administrative Changes Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $3,287 $562 $5,694
125,733
kWh
- $(-2,407.0)
-
MMBtu
-
02 2.1392: Replace purchased steam with other energy source $41,500 $80,000 - $(-59,523.0)
-
MMBtu
$101,023
-
MMBtu
-
03 2.3131: Reschedule plant operations or reduce load to avoid peaks $5,692 - $5,692
-
kWh
- - -
04 3.4157: Replace water cooling on processes with air cooling $4,855 $17,600 $4,855
94,959
kWh
- - -
05 2.6218: Turn off equipment when not in use $4,046 $33,000 $4,046
79,132
kWh
- - -
06 2.6218: Turn off equipment when not in use $3,168 $400 - - - $3,168
TOTAL RECOMMENDED $62,548 $131,562 $20,287
299,824
kWh
$(-59,523.0)
-
MMBtu
$98,616
-
MMBtu
$3,168
TOTAL IMPLEMENTED - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Other Energy Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs