| Assessment Year | 1983 |
|---|---|
| Principal Product | COMMERCIAL PRINTINGS |
| NAICS |
n/a
|
| SIC | 2752: Commercial Printing, Lithographic |
| Sales Range | $10 M to 50M |
| # of Employees | 260 |
| Plant Area |
n/a
|
| Annual Production | 0
units
|
| Production Hrs. Annual | 6,800
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $256,812 | 5,607,855 |
kWh
|
$0.046 |
| Natural Gas | $58,574 | 13,675 |
MMBtu
|
$4.28 |
| Other Energy | $75,605 | 8,267 |
MMBtu
|
$9.15 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $62,548 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Other Energy Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,287 | $562 |
$5,694
125,733
kWh
|
- |
$(-2,407.0)
-
MMBtu
|
- | |
| 02 | 2.1392: Replace purchased steam with other energy source | $41,500 | $80,000 | - |
$(-59,523.0)
-
MMBtu
|
$101,023
-
MMBtu
|
- | |
| 03 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $5,692 | - |
$5,692
-
kWh
|
- | - | - | |
| 04 | 3.4157: Replace water cooling on processes with air cooling | $4,855 | $17,600 |
$4,855
94,959
kWh
|
- | - | - | |
| 05 | 2.6218: Turn off equipment when not in use | $4,046 | $33,000 |
$4,046
79,132
kWh
|
- | - | - | |
| 06 | 2.6218: Turn off equipment when not in use | $3,168 | $400 | - | - | - | $3,168 | |
| TOTAL RECOMMENDED | $62,548 | $131,562 |
$20,287
299,824
kWh
|
$(-59,523.0)
-
MMBtu
|
$98,616
-
MMBtu
|
$3,168 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Other Energy Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs