Assessment Year | 1982 |
---|---|
Principal Product | MEN'S/WOMEN'S SUITS |
NAICS |
n/a
|
SIC | 2311: Men's and Boys' Suits, Coats, and Overcoats |
Sales Range | $5 M to 10M |
# of Employees | 330 |
Plant Area |
n/a
|
Annual Production | 30,000
pieces
|
Production Hrs. Annual | 1,600
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $85,247 | 1,002,345 |
kWh
|
$0.085 |
Natural Gas | $51,204 | 13,859 |
MMBtu
|
$3.69 |
Fuel Oil #2 | $4,600 | 700 |
MMBtu
|
$6.57 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $17,314 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Fuel Oil #2 Savings |
---|---|---|---|---|---|---|---|
01 | 2.1233: Analyze flue gas for proper air/fuel ratio | $3,843 | $600 | - |
$3,600
-
MMBtu
|
$243
-
MMBtu
|
|
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,175 | $122 |
$2,440
27,843
kWh
|
$(-265.0)
-
MMBtu
|
- | |
03 | 2.2136: Install / repair insulation on steam lines | $4,878 | $2,288 |
$2,362
24,033
kWh
|
$2,516
-
MMBtu
|
- | |
04 | 2.2136: Install / repair insulation on steam lines | $1,352 | $1,500 |
$678
6,741
kWh
|
$674
-
MMBtu
|
- | |
05 | 2.7494: Install storm windows and doors | $5,066 | $6,048 | - |
$5,066
-
MMBtu
|
- | |
TOTAL RECOMMENDED | $17,314 | $10,558 |
$5,480
58,617
kWh
|
$11,591
-
MMBtu
|
$243
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs