ITAC Assessment: UD0044
ITAC logo
ITAC Assessment: UD0044
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1982
Principal Product BITUMINOUS CONCRETE
NAICS
n/a
SIC 3273: Ready-Mixed Concrete
Sales Range $1
M
to 5
M
# of Employees 3
Plant Area
n/a
Annual Production 115,000
ton
Production Hrs. Annual 1,000
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $39,253 439,625
kWh
Fuel Oil #2 $206,909 28,966
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $4,962 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.8118: Check for accuracy of utility / power meters $4,962 $2,000 $4,962
68,288
kWh
TOTAL RECOMMENDED $4,962 $2,000 $4,962
68,288
kWh
TOTAL IMPLEMENTED - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs