ITAC Assessment: UD0031
ITAC logo
ITAC Assessment: UD0031
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1982
Principal Product SUBMERSIBLE ELEC. MOTORS
NAICS
n/a
SIC 3621: Motors and Generators
Sales Range $5
M
to 10
M
# of Employees 92
Plant Area
n/a
Annual Production 66,000
pieces
Production Hrs. Annual 2,125
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $87,171 1,747,655
kWh
Fuel Oil #2 $13,428 1,625
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $5,648 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $256

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Fuel Oil #2 Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $1,292 $228 $1,292
19,050
kWh
-
02 2.6121: Reduce hot water temperature to the minimum required $256 - $256
4,689
kWh
-
03 2.7314: Reduce ventilation air $2,422 $40 $1,204
24,033
kWh
$1,218
-
MMBtu
04 2.7243: Improve air circulation with destratification fans / other methods $1,678 $1,000 - $1,678
-
MMBtu
TOTAL RECOMMENDED $5,648 $1,268 $2,752
47,772
kWh
$2,896
-
MMBtu
TOTAL IMPLEMENTED $256 - $256
4,689
kWh
-
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs