| Assessment Year | 2026 |
|---|---|
| Principal Product | Cold-formed steel framing |
| NAICS | 332322: Sheet Metal Work Manufacturing |
| SIC | 3441: Fabricated Structural Metal |
| Sales Range | $100 M to 500M |
| # of Employees | 98 |
| Plant Area |
259,443
ft2
|
| Annual Production | 110,000,000
units
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | Connecticut |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $303,483 | 1,783,593 |
kWh
|
$0.17 |
| Electricity Demand | $147,596 | 5,515 |
kW-mo/yr
|
$26.76 |
| Electricity Fees | $67,954 | - |
|
- |
| Natural Gas | $146,477 | 14,531 |
MMBtu
|
$10.08 |
| LPG | $39,078 | 2,143 |
MMBtu
|
$18.24 |
| TOTAL YEARLY COSTS | $704,588 | |||
| RECOMMENDED SAVINGS* | $75,689 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.3212: Optimize plant power factor | $25,923 | $14,733 | - | - | $25,923 | |
| 02 | 2.8121: Apply for tax-free status for energy purchases | $21,532 | - | - | - | $21,532 | |
| 03 | 2.8123: Pay utility bills on time | $754 | - | - | - | $754 | |
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,857 | $1,560 |
$2,968
17,441
kWh
|
$889
-
kW-mo/yr
|
- | |
| 05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $4,118 | - |
$3,058
17,967
kWh
|
$1,060
-
kW-mo/yr
|
- | |
| 06 | 2.7135: Install occupancy sensors | $7,251 | $9,750 |
$6,882
40,435
kWh
|
$369
-
kW-mo/yr
|
- | |
| 07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $10,941 | $68,400 |
$8,401
49,358
kWh
|
$2,540
-
kW-mo/yr
|
- | |
| 08 | 2.7135: Install occupancy sensors | $607 | $1,560 |
$551
3,235
kWh
|
$56
-
kW-mo/yr
|
- | |
| 09 | 2.7134: Use photocell controls | $706 | $1,800 |
$642
3,774
kWh
|
$64
-
kW-mo/yr
|
- | |
| TOTAL RECOMMENDED | $75,689 | $97,803 |
$22,502
132,210
kWh
|
$4,978
-
kW-mo/yr
|
$48,209 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs