ITAC Assessment: UC2515
ITAC logo
ITAC Assessment: UC2515
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2025
Principal Product Asphalt
NAICS 324121: Asphalt Paving Mixture and Block Manufacturing
SIC 2951: Asphalt Paving Mixtures and Blocks
Sales Range $5
M
to 10
M
# of Employees 6
Plant Area 447,376
ft2
Annual Production 84,119
ton
Production Hrs. Annual 1,900
hrs
Location (State) Massachusetts

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $31,088 267,120
kWh
Electricity Demand $57,088 2,552
kW-mo/yr
Electricity Fees $2,199 -
LPG $200,938 17,735
MMBtu
Other Gas $119,086 5,413
MMBtu
TOTAL YEARLY COSTS $410,399
RECOMMENDED SAVINGS* $177,043 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings LPG Savings Other Gas Savings Ancillary Material Cost Savings One-time Revenue or Avoided Cost Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $677 $370 $314
2,700
kWh
$362
-
kW-mo/yr
- - - -
02 2.2511: Insulate bare equipment $19,982 $9,655 - - - $19,982
-
MMBtu
- -
03 2.9114: Use solar heat to make electricty $25,271 $169,615 $25,271
170,177
kWh
- - - - -
04 2.8114: Change rate schedules or other changes in utility service $102,262 $420,000 - - - $46,758
-
MMBtu
$(-50,700.0) $106,204
05 2.6126: Keep solid fuels / raw materials dry $23,748 $104,000 - - $23,748
-
MMBtu
- - -
06 2.4231: Reduce the pressure of compressed air to the minimum required $1,176 - $23
199
kWh
$1,153
-
kW-mo/yr
- - - -
07 2.4322: Use or replace with energy efficient substitutes $3,927 $15,750 $1,187
10,193
kWh
$2,740
-
kW-mo/yr
- - - -
TOTAL RECOMMENDED $177,043 $719,390 $26,795
183,269
kWh
$4,256
-
kW-mo/yr
$23,748
-
MMBtu
$66,740
-
MMBtu
$(-50,700.0) $106,204
TOTAL IMPLEMENTED - - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings LPG Savings Other Gas Savings Ancillary Material Cost Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs