Assessment Year | 2023 |
---|---|
Principal Product | Wastewater treatment |
NAICS | 221320: Sewage Treatment Facilities |
SIC | 4952: Sewerage Systems |
Sales Range | $10 M to 50M |
# of Employees | 12 |
Plant Area |
58,600
ft2
|
Annual Production | 2,920,000
Tgal
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Connecticut |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $450,627 | 4,782,240 |
kWh
|
$0.094 |
Electricity Demand | $131,825 | 7,804 |
kW-mo/yr
|
$16.89 |
Electricity Fees | $13,065 | - |
|
- |
Natural Gas | $37,272 | 3,911 |
MMBtu
|
$9.53 |
TOTAL YEARLY COSTS | $632,789 | |||
RECOMMENDED SAVINGS* | $373,272 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,071 | $2,641 |
$947
10,050
kWh
|
$1,019
-
kW-mo/yr
|
- | $44 | - | $61 | |
02 | 2.3192: Use fossil fuel powered generator during peak demand periods | $19,018 | - |
$1,332
14,138
kWh
|
$4,898
-
kW-mo/yr
|
$21,750 | $(-8,962.2) | - | - | |
03 | 2.6231: Utilize controls to operate equipment only when needed | $3,990 | $500 |
$3,085
32,754
kWh
|
$904
-
kW-mo/yr
|
- | - | - | - | |
04 | 2.6231: Utilize controls to operate equipment only when needed | $2,840 | $500 |
$2,283
24,235
kWh
|
$557
-
kW-mo/yr
|
- | - | - | - | |
05 | 2.9114: Use solar heat to make electricty | $279,536 | $1,875,313 |
$222,382
2,360,744
kWh
|
$88,774
-
kW-mo/yr
|
- | - | $(-31,620.0) | - | |
06 | 2.3141: Use battery storage for demand control | $65,817 | $383,577 |
$(-9,233.0)
(-98,013)
kWh
|
$81,072
-
kW-mo/yr
|
- | - | $(-6,021.7) | - | |
TOTAL RECOMMENDED | $373,272 | $2,262,531 |
$220,796
2,343,908
kWh
|
$177,224
-
kW-mo/yr
|
$21,750 | $(-8,917.9) | $(-37,641.7) | $61 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs