| Assessment Year | 2013 |
|---|---|
| Principal Product | Iron pipe |
| NAICS | 331210: Iron and Steel Pipe and Tube Manufacturing from Purchased Steel |
| SIC | 3317: Steel Pipe and Tubes |
| Sales Range | $100 M to 500M |
| # of Employees | 450 |
| Plant Area |
625,000
ft2
|
| Annual Production | 274,723
ton
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Alabama |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $2,559,240 | 40,511,088 |
kWh
|
$0.063 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $263,273 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $71,086 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings |
|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $115,835 | $27,390 |
$115,835
1,832,827
kWh
|
|
| 02 | 2.4224: Upgrade controls on compressors | $76,352 | $32,825 |
$76,352
1,208,100
kWh
|
|
| 03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $71,086 | $800 |
$71,086
1,137,380
kWh
|
|
| TOTAL RECOMMENDED | $263,273 | $61,015 |
$263,273
4,178,307
kWh
|
||
| TOTAL IMPLEMENTED | $71,086 | $800 |
$71,086
1,137,380
kWh
|
||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs