Assessment Year | 2013 |
---|---|
Principal Product | Iron pipe |
NAICS | 331210: Iron and Steel Pipe and Tube Manufacturing from Purchased Steel |
SIC | 3317: Steel Pipe and Tubes |
Sales Range | $100 M to 500M |
# of Employees | 450 |
Plant Area |
625,000
ft2
|
Annual Production | 274,723
ton
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Alabama |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $2,559,240 | 40,511,088 |
kWh
|
$0.063 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $263,273 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $71,086 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings |
---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $115,835 | $27,390 |
$115,835
1,832,827
kWh
|
|
02 | 2.4224: Upgrade controls on compressors | $76,352 | $32,825 |
$76,352
1,208,100
kWh
|
|
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $71,086 | $800 |
$71,086
1,137,380
kWh
|
|
TOTAL RECOMMENDED | $263,273 | $61,015 |
$263,273
4,178,307
kWh
|
||
TOTAL IMPLEMENTED | $71,086 | $800 |
$71,086
1,137,380
kWh
|
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs