ITAC Assessment: UA3030
ITAC logo
ITAC Assessment: UA3030
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2013
Principal Product Iron pipe
NAICS 331210: Iron and Steel Pipe and Tube Manufacturing from Purchased Steel
SIC 3317: Steel Pipe and Tubes
Sales Range $100
M
to 500
M
# of Employees 450
Plant Area 625,000
ft2
Annual Production 274,723
ton
Production Hrs. Annual 8,760
hrs
Location (State) Alabama

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $2,559,240 40,511,088
kWh
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $263,273 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $71,086

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $115,835 $27,390 $115,835
1,832,827
kWh
02 2.4224: Upgrade controls on compressors $76,352 $32,825 $76,352
1,208,100
kWh
03 2.4231: Reduce the pressure of compressed air to the minimum required $71,086 $800 $71,086
1,137,380
kWh
TOTAL RECOMMENDED $263,273 $61,015 $263,273
4,178,307
kWh
TOTAL IMPLEMENTED $71,086 $800 $71,086
1,137,380
kWh
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs