Assessment Year | 2011 |
---|---|
Principal Product | Diesel Engines |
NAICS | 336310: Motor Vehicle Gasoline Engine and Engine Parts Manufacturing |
SIC | 3714: Motor Vehicle Parts and Accessories |
Sales Range | $50 M to 100M |
# of Employees | 999 |
Plant Area |
544,000
ft2
|
Annual Production | 1,000
units
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Alabama |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $2,571,133 | 49,444,865 |
kWh
|
$0.052 |
Electricity Demand | $693,252 | 94,064 |
kW-mo/yr
|
$7.37 |
Natural Gas | $155,849 | 11,718 |
MMBtu
|
$13.30 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $657,177 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $105,208 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.7224: Reduce space conditioning during non-working hours | $78,640 | $8,320 |
$39,260
755,000
kWh
|
$10,466
-
kW-mo/yr
|
$28,914
-
MMBtu
|
|
02 | 2.7241: Install outside air damper / economizer on hvac unit | $71,901 | $30,750 |
$66,300
1,275,000
kWh
|
$5,601
-
kW-mo/yr
|
- | |
03 | 2.7211: Clean and maintain refrigerant condensers and towers | $72,048 | $98,000 |
$49,348
949,000
kWh
|
$22,700
-
kW-mo/yr
|
- | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $16,700 | $60,860 |
$13,125
252,396
kWh
|
$3,575
-
kW-mo/yr
|
- | |
05 | 2.7135: Install occupancy sensors | $20,767 | $13,730 |
$20,767
399,360
kWh
|
- | - | |
06 | 2.7122: Disconnect ballasts | $5,801 | $405 |
$4,556
87,610
kWh
|
$1,245
-
kW-mo/yr
|
- | |
07 | 2.3212: Optimize plant power factor | $29,663 | $26,400 | - |
$29,663
-
kW-mo/yr
|
- | |
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $92,285 | $51,748 |
$72,519
1,394,593
kWh
|
$19,766
-
kW-mo/yr
|
- | |
09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $269,372 | $630,225 |
$211,680
4,070,773
kWh
|
$57,692
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $657,177 | $920,438 |
$477,555
9,183,732
kWh
|
$150,708
-
kW-mo/yr
|
$28,914
-
MMBtu
|
||
TOTAL IMPLEMENTED | $105,208 | $22,455 |
$64,583
1,241,970
kWh
|
$11,711
-
kW-mo/yr
|
$28,914
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs