ITAC Assessment: UA0270
ITAC logo
ITAC Assessment: UA0270
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2023
Principal Product PTFE Fibers
NAICS 325220: Artificial and Synthetic Fibers and Filaments Manufacturing
SIC 2824: Manmade Organic Fibers, Except Cellulosic
Sales Range $10
M
to 50
M
# of Employees 50
Plant Area 79,571
ft2
Annual Production 50,000
units
Production Hrs. Annual 8,760
hrs
Location (State) Alabama

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $329,315 4,839,017
kWh
Natural Gas $61,776 9,005
MMBtu
TOTAL YEARLY COSTS $391,091
RECOMMENDED SAVINGS* $5,772 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $1,638

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.4239: Eliminate or reduce compressed air usage $2,529 $400 $2,529
37,142
kWh
02 2.7142: Utilize higher efficiency lamps and/or ballasts $1,638 $395 $1,638
24,050
kWh
03 2.7135: Install occupancy sensors $1,605 $481 $1,605
23,568
kWh
TOTAL RECOMMENDED $5,772 $1,276 $5,772
84,760
kWh
TOTAL IMPLEMENTED $1,638 $395 $1,638
24,050
kWh
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs