Assessment Year | 1999 |
---|---|
Principal Product | Semiconductor Etching Equipment |
NAICS |
n/a
|
SIC | 3344: |
Sales Range | $10 M to 50M |
# of Employees | 140 |
Plant Area |
70,000
ft2
|
Annual Production | 84
pieces
|
Production Hrs. Annual | 2,832
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $100,452 | 1,703,107 |
kWh
|
$0.059 |
Electricity Demand | $54,121 | 4,017 |
kW-mo/yr
|
$13.47 |
Natural Gas | $73,673 | 15,662 |
MMBtu
|
$4.70 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $16,708 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Solid Waste (haz) Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7135: Install occupancy sensors | $1,976 | $1,080 | n/a |
$1,020
17,292
kWh
|
$956
-
kW-mo/yr
|
- | - |
02 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,410 | $948 | n/a |
$968
16,413
kWh
|
$442
-
kW-mo/yr
|
- | - |
03 | 2.7144: Install spectral reflectors / delamp | $2,892 | $4,850 | n/a |
$1,941
32,825
kWh
|
$951
-
kW-mo/yr
|
- | - |
04 | 3.5316: Contract a wood pallet recycling company | $1,320 | $200 | n/a | - | - |
$1,320
-
lb
|
- |
05 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $590 | $200 | n/a | - | - |
$590
-
lb
|
- |
06 | 3.7196: Use re-usable filters | $8,520 | $6,390 | n/a | - | - | - |
$8,520
-
lb
|
TOTAL RECOMMENDED | $16,708 | $13,668 |
$3,929
66,530
kWh
|
$2,349
-
kW-mo/yr
|
$1,910
-
lb
|
$8,520
-
lb
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Solid Waste (haz) Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs