ITAC Assessment: UA0264
ITAC logo
ITAC Assessment: UA0264
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2023
Principal Product Wooden doors
NAICS 321911: Wood Window and Door Manufacturing
SIC 2431: Millwork
Sales Range $50
M
to 100
M
# of Employees 289
Plant Area 150,000
ft2
Annual Production 3,380,000
units
Production Hrs. Annual 6,318
hrs
Location (State) Alabama

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $310,812 3,844,916
kWh
Electricity Fees $32,014 -
Natural Gas $50,196 6,134
MMBtu
TOTAL YEARLY COSTS $393,022
RECOMMENDED SAVINGS* $43,285 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $36,735

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Fees Savings Natural Gas Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $14,745 $4,870 $13,368
165,366
kWh
$1,377 -
02 2.4231: Reduce the pressure of compressed air to the minimum required $9,878 $500 $8,956
110,788
kWh
$922 -
03 2.2437: Recover waste heat from equipment $9,549 $8,397 - - $9,549
-
MMBtu
04 2.7142: Utilize higher efficiency lamps and/or ballasts $2,563 $1,200 $2,324
28,747
kWh
$239 -
05 2.7135: Install occupancy sensors $5,008 $3,605 $4,540
56,164
kWh
$468 -
06 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,542 $1,512 $1,398
17,296
kWh
$144 -
TOTAL RECOMMENDED $43,285 $20,084 $30,586
378,361
kWh
$3,150 $9,549
-
MMBtu
TOTAL IMPLEMENTED $36,735 $14,967 $24,648
304,901
kWh
$2,538 $9,549
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Fees Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs