Assessment Year | 2023 |
---|---|
Principal Product | Wooden doors |
NAICS | 321911: Wood Window and Door Manufacturing |
SIC | 2431: Millwork |
Sales Range | $50 M to 100M |
# of Employees | 289 |
Plant Area |
150,000
ft2
|
Annual Production | 3,380,000
units
|
Production Hrs. Annual | 6,318
hrs
|
Location (State) | Alabama |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $310,812 | 3,844,916 |
kWh
|
$0.081 |
Electricity Fees | $32,014 | - |
|
- |
Natural Gas | $50,196 | 6,134 |
MMBtu
|
$8.18 |
TOTAL YEARLY COSTS | $393,022 | |||
RECOMMENDED SAVINGS* | $43,285 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $36,735 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Fees Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $14,745 | $4,870 |
$13,368
165,366
kWh
|
$1,377 | - | |
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $9,878 | $500 |
$8,956
110,788
kWh
|
$922 | - | |
03 | 2.2437: Recover waste heat from equipment | $9,549 | $8,397 | - | - |
$9,549
-
MMBtu
|
|
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,563 | $1,200 |
$2,324
28,747
kWh
|
$239 | - | |
05 | 2.7135: Install occupancy sensors | $5,008 | $3,605 |
$4,540
56,164
kWh
|
$468 | - | |
06 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,542 | $1,512 |
$1,398
17,296
kWh
|
$144 | - | |
TOTAL RECOMMENDED | $43,285 | $20,084 |
$30,586
378,361
kWh
|
$3,150 |
$9,549
-
MMBtu
|
||
TOTAL IMPLEMENTED | $36,735 | $14,967 |
$24,648
304,901
kWh
|
$2,538 |
$9,549
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Fees Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs