ITAC Assessment: UA0240
ITAC logo
ITAC Assessment: UA0240
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2021
Principal Product Automotive stampings
NAICS 336370: Motor Vehicle Metal Stamping
SIC 3465: Automotive Stampings
Sales Range $1
M
to 5
M
# of Employees 700
Plant Area 500,000
ft2
Annual Production 2,000,000
units
Production Hrs. Annual 8,760
hrs
Location (State) Alabama

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $697,923 12,095,882
kWh
Electricity Demand $137,837 29,368
kW-mo/yr
Electricity Fees $67,403 -
TOTAL YEARLY COSTS $903,163
RECOMMENDED SAVINGS* $37,481 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $37,481

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings
01 2.8114: Change rate schedules or other changes in utility service $10,059 $800 - - $10,059
02 2.3212: Optimize plant power factor $8,528 $60,000 - $8,528
-
kW-mo/yr
-
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $18,894 $9,682 $18,894
276,449
kWh
- -
TOTAL RECOMMENDED $37,481 $70,482 $18,894
276,449
kWh
$8,528
-
kW-mo/yr
$10,059
TOTAL IMPLEMENTED $37,481 $70,482 $18,894
276,449
kWh
$8,528
-
kW-mo/yr
$10,059
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs