Assessment Year | 2005 |
---|---|
Principal Product | automotive parts |
NAICS | 336310: Motor Vehicle Gasoline Engine and Engine Parts Manufacturing |
SIC | 3714: Motor Vehicle Parts and Accessories |
Sales Range | $100 M to 500M |
# of Employees | 500 |
Plant Area |
93,000
ft2
|
Annual Production | 275,000
pieces
|
Production Hrs. Annual | 6,600
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $322,420 | 3,949,375 |
kWh
|
$0.082 |
Electricity Demand | $140,130 | 10,560 |
kW-mo/yr
|
$13.27 |
Electricity Fees | $36,705 | - |
|
- |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $374,245 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $311,684 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Administrative Changes Savings | Primary Raw Material Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,551 | $700 |
$1,197
13,728
kWh
|
$354
-
kW-mo/yr
|
- | - | - | |
02 | 2.4133: Use most efficient type of electric motors | $148 | $308 |
$114
1,731
kWh
|
$34
-
kW-mo/yr
|
- | - | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,413 | $6,375 |
$4,076
46,722
kWh
|
$1,337
-
kW-mo/yr
|
- | - | - | |
04 | 4.126: Install sensors to detect defects | $94,133 | $49,500 |
$3,224
39,493
kWh
|
- | - | - | $90,909 | |
05 | 4.625: Develop standard operating procedures | $216,000 | $11,800 | - | - | $216,000 | - | - | |
06 | 4.423: Move product using mechanical means | $30,000 | $20,000 | - | - | - | $30,000 | - | |
07 | 4.441: Install automatic packing equipment | $27,000 | $50,000 | - | - | $27,000 | - | - | |
TOTAL RECOMMENDED | $374,245 | $138,683 |
$8,611
101,674
kWh
|
$1,725
-
kW-mo/yr
|
$243,000 | $30,000 | $90,909 | ||
TOTAL IMPLEMENTED | $311,684 | $62,000 |
$4,421
53,221
kWh
|
$354
-
kW-mo/yr
|
$216,000 | - | $90,909 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Administrative Changes Savings | Primary Raw Material Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs