Assessment Year | 2021 |
---|---|
Principal Product | Automotive components |
NAICS | 336111: Automobile Manufacturing |
SIC | 3711: Motor Vehicles and Passenger Car Bodies |
Sales Range | $10 M to 50M |
# of Employees | 240 |
Plant Area |
560,000
ft2
|
Annual Production | 3,800,000
units
|
Production Hrs. Annual | 4,896
hrs
|
Location (State) | Alabama |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $605,365 | 10,104,246 |
kWh
|
$0.060 |
Electricity Demand | $144,095 | 30,149 |
kW-mo/yr
|
$4.78 |
Electricity Fees | $35,832 | - |
|
- |
Natural Gas | $160,296 | 21,761 |
MMBtu
|
$7.37 |
TOTAL YEARLY COSTS | $945,588 | |||
RECOMMENDED SAVINGS* | $64,196 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $39,814 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $6,903 | $5,078 |
$5,510
91,974
kWh
|
$1,078
-
kW-mo/yr
|
$315 | - | |
02 | 2.3212: Optimize plant power factor | $16,096 | $8,577 | - |
$13,321
-
kW-mo/yr
|
$2,775 | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,979 | $2,094 |
$1,781
29,732
kWh
|
$108
-
kW-mo/yr
|
$90 | - | |
04 | 2.4235: Remove or close off unneeded compressed air lines | $10,001 | $808 |
$9,545
159,314
kWh
|
- | $456 | - | |
05 | 2.7224: Reduce space conditioning during non-working hours | $26,697 | $150 |
$20,010
333,999
kWh
|
- | $956 |
$5,731
-
MMBtu
|
|
06 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $1,383 | $708 |
$2,191
36,576
kWh
|
- | $105 |
$(-913.0)
-
MMBtu
|
|
07 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,137 | $81 |
$875
14,610
kWh
|
$210
-
kW-mo/yr
|
$52 | - | |
TOTAL RECOMMENDED | $64,196 | $17,496 |
$39,912
666,205
kWh
|
$14,717
-
kW-mo/yr
|
$4,749 |
$4,818
-
MMBtu
|
||
TOTAL IMPLEMENTED | $39,814 | $3,133 |
$32,211
537,655
kWh
|
$318
-
kW-mo/yr
|
$1,554 |
$5,731
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs