ITAC Assessment: UA0221
ITAC logo
ITAC Assessment: UA0221
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2020
Principal Product soft drinks
NAICS 312111: Soft Drink Manufacturing
SIC 2086: Bottled and Canned Soft Drinks and Carbonated Waters
Sales Range $10
M
to 50
M
# of Employees 120
Plant Area 35,287
ft2
Annual Production 73,968
Tgal
Production Hrs. Annual 4,800
hrs
Location (State) Alabama

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $592,477 10,644,200
kWh
Electricity Demand $92,194 21,994
kW-mo/yr
Electricity Fees $26,590 -
Natural Gas $227,857 28,169
MMBtu
Waste Disposal Costs
Water Usage $501,626 94,076
Tgal
TOTAL YEARLY COSTS $1,440,744
RECOMMENDED SAVINGS* $32,473 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $19,780

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $4,796 $7,800 $3,922
70,464
kWh
$738
-
kW-mo/yr
$136
02 2.4231: Reduce the pressure of compressed air to the minimum required $9,795 $50 $8,403
150,975
kWh
$1,115
-
kW-mo/yr
$277
03 2.4235: Remove or close off unneeded compressed air lines $9,121 - $8,863
159,242
kWh
- $258
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $5,863 $4,000 $5,068
91,045
kWh
$629
-
kW-mo/yr
$166
05 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $2,898 $8,350 $2,816
50,571
kWh
- $82
TOTAL RECOMMENDED $32,473 $20,200 $29,072
522,297
kWh
$2,482
-
kW-mo/yr
$919
TOTAL IMPLEMENTED $19,780 $11,800 $17,853
320,751
kWh
$1,367
-
kW-mo/yr
$560
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs