Assessment Year | 2020 |
---|---|
Principal Product | soft drinks |
NAICS | 312111: Soft Drink Manufacturing |
SIC | 2086: Bottled and Canned Soft Drinks and Carbonated Waters |
Sales Range | $10 M to 50M |
# of Employees | 120 |
Plant Area |
35,287
ft2
|
Annual Production | 73,968
Tgal
|
Production Hrs. Annual | 4,800
hrs
|
Location (State) | Alabama |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $592,477 | 10,644,200 |
kWh
|
$0.056 | |
Electricity Demand | $92,194 | 21,994 |
kW-mo/yr
|
$4.19 | |
Electricity Fees | $26,590 | - |
|
- | |
Natural Gas | $227,857 | 28,169 |
MMBtu
|
$8.09 | |
Waste Disposal Costs | |||||
Water Usage | $501,626 | 94,076 |
Tgal
|
$5.33 | |
TOTAL YEARLY COSTS | $1,440,744 | ||||
RECOMMENDED SAVINGS* | $32,473 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $19,780 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,796 | $7,800 |
$3,922
70,464
kWh
|
$738
-
kW-mo/yr
|
$136 | |
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $9,795 | $50 |
$8,403
150,975
kWh
|
$1,115
-
kW-mo/yr
|
$277 | |
03 | 2.4235: Remove or close off unneeded compressed air lines | $9,121 | - |
$8,863
159,242
kWh
|
- | $258 | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $5,863 | $4,000 |
$5,068
91,045
kWh
|
$629
-
kW-mo/yr
|
$166 | |
05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $2,898 | $8,350 |
$2,816
50,571
kWh
|
- | $82 | |
TOTAL RECOMMENDED | $32,473 | $20,200 |
$29,072
522,297
kWh
|
$2,482
-
kW-mo/yr
|
$919 | ||
TOTAL IMPLEMENTED | $19,780 | $11,800 |
$17,853
320,751
kWh
|
$1,367
-
kW-mo/yr
|
$560 |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs