Assessment Year | 2020 |
---|---|
Principal Product | Fire Hydrants |
NAICS | 331511: Iron Foundries |
SIC | 3321: Gray and Ductile Iron Foundries |
Sales Range | $100 M to 500M |
# of Employees | 487 |
Plant Area |
440,481
ft2
|
Annual Production | 24,682
ton
|
Production Hrs. Annual | 5,500
hrs
|
Location (State) | Alabama |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $2,660,694 | 59,296,506 |
kWh
|
$0.045 |
Electricity Fees | $(-540,463.0) | - |
|
- |
Natural Gas | $470,151 | 76,053 |
MMBtu
|
$6.18 |
TOTAL YEARLY COSTS | $2,590,382 | |||
RECOMMENDED SAVINGS* | $235,086 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $9,211 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Fees Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $14,378 | $34,203 |
$18,042
402,084
kWh
|
$(-3,664.0) | - | |
02 | 2.2414: Use waste heat from hot flue gases to preheat | $10,117 | $42,000 | - | - |
$10,117
-
MMBtu
|
|
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $9,211 | $4,195 |
$11,559
257,605
kWh
|
$(-2,348.0) | - | |
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $12,615 | $400 |
$15,830
352,786
kWh
|
$(-3,215.0) | - | |
05 | 2.4226: Use / purchase optimum sized compressor | $183,880 | $820,000 |
$230,744
5,142,387
kWh
|
$(-46,864.0) | - | |
06 | 2.4133: Use most efficient type of electric motors | $4,885 | $9,300 |
$6,130
136,621
kWh
|
$(-1,245.0) | - | |
TOTAL RECOMMENDED | $235,086 | $910,098 |
$282,305
6,291,483
kWh
|
$(-57,336.0) |
$10,117
-
MMBtu
|
||
TOTAL IMPLEMENTED | $9,211 | $4,195 |
$11,559
257,605
kWh
|
$(-2,348.0) | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Fees Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs