| Assessment Year | 2018 |
|---|---|
| Principal Product | Bread |
| NAICS | 311811: Retail Bakeries |
| SIC | 2051: Bread and Other Bakery Products, Except Cookies and Crackers |
| Sales Range | $50 M to 100M |
| # of Employees | 120 |
| Plant Area |
87,000
ft2
|
| Annual Production | 45,000,000
lb
|
| Production Hrs. Annual | 8,597
hrs
|
| Location (State) | Georgia |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $257,263 | 4,813,500 |
kWh
|
$0.053 |
| Electricity Demand | $39,696 | 9,694 |
kW-mo/yr
|
$4.09 |
| Electricity Fees | $42,570 | - |
|
- |
| Natural Gas | $225,215 | 26,842 |
MMBtu
|
$8.39 |
| TOTAL YEARLY COSTS | $564,744 | |||
| RECOMMENDED SAVINGS* | $51,550 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $16,288 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.2437: Recover waste heat from equipment | $21,964 | $45,000 | - | - | - |
$21,964
-
MMBtu
|
|
| 02 | 2.6218: Turn off equipment when not in use | $13,298 | $50 | - | - | - |
$13,298
-
MMBtu
|
|
| 03 | 2.2163: Use minimum steam operating pressure | $3,482 | $50 | - | - | - |
$3,482
-
MMBtu
|
|
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,745 | $5,828 |
$4,813
90,058
kWh
|
$594
-
kW-mo/yr
|
$338 | - | |
| 05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $3,704 | $100 |
$3,113
58,242
kWh
|
$373
-
kW-mo/yr
|
$218 | - | |
| 06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,357 | $3,000 |
$2,860
53,509
kWh
|
$300
-
kW-mo/yr
|
$197 | - | |
| TOTAL RECOMMENDED | $51,550 | $54,028 |
$10,786
201,809
kWh
|
$1,267
-
kW-mo/yr
|
$753 |
$38,744
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $16,288 | $8,978 |
$10,786
201,809
kWh
|
$1,267
-
kW-mo/yr
|
$753 |
$3,482
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs