Assessment Year | 2018 |
---|---|
Principal Product | Processed Chicken |
NAICS | 311615: Poultry Processing |
SIC | 2015: Poultry Slaughtering and Processing |
Sales Range | $100 M to 500M |
# of Employees | 352 |
Plant Area |
50,000
ft2
|
Annual Production | 51,272,881
units
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Alabama |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $751,353 | 13,913,597 |
kWh
|
$0.054 | |
Electricity Demand | $147,000 | 34,230 |
kW-mo/yr
|
$4.29 | |
Electricity Fees | $46,977 | - |
|
- | |
Natural Gas | $399,984 | 46,308 |
MMBtu
|
$8.64 | |
Waste Disposal Costs | |||||
Water Usage | $732,983 | 24,012,800 |
Tgal
|
$0.031 | |
TOTAL YEARLY COSTS | $2,078,297 | ||||
RECOMMENDED SAVINGS* | $121,469 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $11,650 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.2437: Recover waste heat from equipment | $81,560 | $200,000 | - | - | - |
$81,560
-
MMBtu
|
|
02 | 2.1113: Reduce combustion air flow to optimum | $2,707 | $7,500 | - | - | - |
$2,707
-
MMBtu
|
|
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $25,552 | $64,329 |
$21,686
401,582
kWh
|
$2,596
-
kW-mo/yr
|
$1,270 | - | |
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $5,516 | $500 |
$4,196
77,696
kWh
|
$1,046
-
kW-mo/yr
|
$274 | - | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,745 | $2,465 |
$3,998
74,036
kWh
|
$511
-
kW-mo/yr
|
$236 | - | |
06 | 2.6218: Turn off equipment when not in use | $1,389 | $737 |
$1,320
24,450
kWh
|
- | $69 | - | |
TOTAL RECOMMENDED | $121,469 | $275,531 |
$31,200
577,764
kWh
|
$4,153
-
kW-mo/yr
|
$1,849 |
$84,267
-
MMBtu
|
||
TOTAL IMPLEMENTED | $11,650 | $3,702 |
$9,514
176,182
kWh
|
$1,557
-
kW-mo/yr
|
$579 | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs