| Assessment Year | 2017 |
|---|---|
| Principal Product | Automotive Interiors |
| NAICS | 326199: All Other Plastics Product Manufacturing |
| SIC | 3714: Motor Vehicle Parts and Accessories |
| Sales Range | $10 M to 50M |
| # of Employees | 300 |
| Plant Area |
294,000
ft2
|
| Annual Production | 19,805,500
units
|
| Production Hrs. Annual | 6,000
hrs
|
| Location (State) | Alabama |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $1,002,691 | 18,740,944 |
kWh
|
$0.054 |
| Electricity Demand | $194,750 | 41,492 |
kW-mo/yr
|
$4.69 |
| Electricity Fees | $82,298 | - |
|
- |
| Natural Gas | $6,701 | 587 |
MMBtu
|
$11.42 |
| TOTAL YEARLY COSTS | $1,286,440 | |||
| RECOMMENDED SAVINGS* | $168,885 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $36,297 | $94,071 |
$29,444
550,354
kWh
|
$5,167
-
kW-mo/yr
|
$1,686 | |
| 02 | 2.7241: Install outside air damper / economizer on hvac unit | $105,154 | $36,000 |
$100,271
1,874,218
kWh
|
- | $4,883 | |
| 03 | 2.2437: Recover waste heat from equipment | $4,924 | $6,004 |
$4,695
87,760
kWh
|
- | $229 | |
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $6,765 | $1,285 |
$5,396
100,852
kWh
|
$1,055
-
kW-mo/yr
|
$314 | |
| 05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,492 | $250 |
$1,914
35,769
kWh
|
$462
-
kW-mo/yr
|
$116 | |
| 06 | 2.3212: Optimize plant power factor | $12,098 | $21,400 | - |
$11,536
-
kW-mo/yr
|
$562 | |
| 07 | 2.2511: Insulate bare equipment | $1,155 | $2,485 |
$815
15,228
kWh
|
$286
-
kW-mo/yr
|
$54 | |
| TOTAL RECOMMENDED | $168,885 | $161,495 |
$142,535
2,664,181
kWh
|
$18,506
-
kW-mo/yr
|
$7,844 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs