| Assessment Year | 2015 |
|---|---|
| Principal Product | Cedar Oil |
| NAICS | 321999: All Other Miscellaneous Wood Product Manufacturing |
| SIC | 2499: Wood Products, Not Elsewhere Classified |
| Sales Range | $5 M to 10M |
| # of Employees | 41 |
| Plant Area |
150,000
ft2
|
| Annual Production | 440,920
lb
|
| Production Hrs. Annual | 8,064
hrs
|
| Location (State) | Alabama |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $275,467 | 4,258,522 |
kWh
|
$0.065 |
| Electricity Demand | $152,659 | 15,790 |
kW-mo/yr
|
$9.67 |
| Electricity Fees | $19,554 | - |
|
- |
| Wood | $175,000 | 113,100 |
MMBtu
|
$1.55 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $187,709 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $27,671 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Wood Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.3321: Use steam pressure reduction to generate power | $63,096 | $121,500 |
$70,424
1,088,640
kWh
|
$15,662
-
kW-mo/yr
|
$3,306 |
$(-26,296.0)
-
MMBtu
|
|
| 02 | 2.1113: Reduce combustion air flow to optimum | $45,863 | $7,500 | - | - | - |
$45,863
-
MMBtu
|
|
| 03 | 2.2414: Use waste heat from hot flue gases to preheat | $43,191 | $40,000 | - | - | - |
$43,191
-
MMBtu
|
|
| 04 | 2.2136: Install / repair insulation on steam lines | $23,276 | $3,627 | - | - | - |
$23,276
-
MMBtu
|
|
| 05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $5,428 | $2,268 |
$5,227
80,794
kWh
|
- | $201 | - | |
| 06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $4,395 | $800 |
$2,666
41,206
kWh
|
$1,566
-
kW-mo/yr
|
$163 | - | |
| 07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,460 | $2,995 |
$1,557
24,073
kWh
|
$812
-
kW-mo/yr
|
$91 | - | |
| TOTAL RECOMMENDED | $187,709 | $178,690 |
$79,874
1,234,713
kWh
|
$18,040
-
kW-mo/yr
|
$3,761 |
$86,034
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $27,671 | $4,427 |
$2,666
41,206
kWh
|
$1,566
-
kW-mo/yr
|
$163 |
$23,276
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Wood Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs