Assessment Year | 2015 |
---|---|
Principal Product | Bio-oil |
NAICS | 311613: Rendering and Meat Byproduct Processing |
SIC | 2077: Animal and Marine Fats and Oils |
Sales Range | $1 M to 5M |
# of Employees | 6 |
Plant Area |
10,360
ft2
|
Annual Production | 12,000,000
lb
|
Production Hrs. Annual | 2,340
hrs
|
Location (State) | Alabama |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $21,350 | 207,120 |
kWh
|
$0.10 |
Electricity Demand | $8,973 | 1,893 |
kW-mo/yr
|
$4.74 |
Electricity Fees | $2,393 | - |
|
- |
Natural Gas | $6,509 | 1,070 |
MMBtu
|
$6.08 |
Fuel Oil #2 | $65,110 | 2,512 |
MMBtu
|
$25.92 |
Other Energy | $5,571 | 300 |
MMBtu
|
$18.57 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $33,190 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Fuel Oil #2 Savings | Other Energy Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.1331: Burn a less expensive grade of fuel | $27,518 | - | - | - | - |
$(-9,108.0)
-
MMBtu
|
$31,062
-
MMBtu
|
$5,564
-
MMBtu
|
|
02 | 2.2136: Install / repair insulation on steam lines | $671 | $658 | - | - | - |
$96
-
MMBtu
|
$575
-
MMBtu
|
- | |
03 | 2.3212: Optimize plant power factor | $3,174 | $3,210 | - |
$3,024
-
kW-mo/yr
|
$150 | - | - | - | |
04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $1,270 | $3,920 |
$1,210
11,734
kWh
|
- | $60 | - | - | - | |
05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $557 | $186 |
$361
3,501
kWh
|
$170
-
kW-mo/yr
|
$26 | - | - | - | |
TOTAL RECOMMENDED | $33,190 | $7,974 |
$1,571
15,235
kWh
|
$3,194
-
kW-mo/yr
|
$236 |
$(-9,012.0)
-
MMBtu
|
$31,637
-
MMBtu
|
$5,564
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs