ITAC Assessment: UA0131
ITAC logo
ITAC Assessment: UA0131
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2014
Principal Product Protein and Oil
NAICS 311613: Rendering and Meat Byproduct Processing
SIC 2077: Animal and Marine Fats and Oils
Sales Range $10
M
to 50
M
# of Employees 26
Plant Area 20,000
ft2
Annual Production 135,500,000
lb
Production Hrs. Annual 6,732
hrs
Location (State) Alabama

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $278,688 4,047,693
kWh
Electricity Fees $29,826 -
Natural Gas $576,692 118,175
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $33,424 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $6,471

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Fees Savings Natural Gas Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $5,273 $10,071 $4,972
72,218
kWh
$301 -
02 2.2136: Install / repair insulation on steam lines $6,471 $2,508 - - $6,471
-
MMBtu
03 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $1,501 $4,321 $1,415
20,555
kWh
$86 -
04 2.2414: Use waste heat from hot flue gases to preheat $20,179 $127,000 - - $20,179
-
MMBtu
TOTAL RECOMMENDED $33,424 $143,900 $6,387
92,773
kWh
$387 $26,650
-
MMBtu
TOTAL IMPLEMENTED $6,471 $2,508 - - $6,471
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs