| Assessment Year | 2014 |
|---|---|
| Principal Product | lumber |
| NAICS | 321113: Sawmills |
| SIC | 2421: Sawmills and Planing Mills, General |
| Sales Range | $10 M to 50M |
| # of Employees | 60 |
| Plant Area |
80,000
ft2
|
| Annual Production | 35,000,000
units
|
| Production Hrs. Annual | 2,340
hrs
|
| Location (State) | Alabama |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $361,129 | 4,887,626 |
kWh
|
$0.074 |
| Electricity Demand | $0.0 | 23,066 |
kW-mo/yr
|
$0.000 |
| Electricity Fees | $26,577 | - |
|
- |
| Wood | $115,668 | 53,989 |
MMBtu
|
$2.14 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $95,239 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $13,695 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Fees Savings | Wood Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $8,710 | $9,095 |
$8,234
111,429
kWh
|
$476 | - | |
| 02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $45,368 | $18,153 |
$42,889
580,372
kWh
|
$2,479 | - | |
| 03 | 2.2136: Install / repair insulation on steam lines | $10,240 | $3,495 | - | - |
$10,240
-
MMBtu
|
|
| 04 | 2.1113: Reduce combustion air flow to optimum | $4,096 | $7,500 | - | - |
$4,096
-
MMBtu
|
|
| 05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $3,455 | $1,870 |
$3,266
44,193
kWh
|
$189 | - | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,117 | $8,661 |
$2,001
27,078
kWh
|
$116 | - | |
| 07 | 4.454: Modify startup/shutdown times | $15,087 | - | - | $15,087 | - | |
| 08 | 4.821: Pay bills on time to avoid late fees | $6,166 | - | - | $6,166 | - | |
| TOTAL RECOMMENDED | $95,239 | $48,774 |
$56,390
763,072
kWh
|
$24,513 |
$14,336
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $13,695 | $5,365 |
$3,266
44,193
kWh
|
$189 |
$10,240
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Fees Savings | Wood Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs