| Assessment Year | 2013 |
|---|---|
| Principal Product | Fabricated Metal Products |
| NAICS | 332313: Plate Work Manufacturing |
| SIC | 3499: Fabricated Metal Products, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 208 |
| Plant Area |
125,000
ft2
|
| Annual Production | 19,756
pieces
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | Mississippi |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $167,096 | 2,670,648 |
kWh
|
$0.063 |
| Electricity Demand | $28,391 | 9,024 |
kW-mo/yr
|
$3.15 |
| Electricity Fees | $13,542 | - |
|
- |
| LPG | $44,482 | 2,518 |
MMBtu
|
$17.67 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $50,346 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $7,226 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | LPG Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.2437: Recover waste heat from equipment | $8,477 | $15,565 |
$8,019
128,158
kWh
|
- | $458 | - | - | |
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,498 | $2,500 |
$2,840
45,390
kWh
|
$469
-
kW-mo/yr
|
$189 | - | - | |
| 03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $4,514 | $1,600 |
$3,816
60,987
kWh
|
$454
-
kW-mo/yr
|
$244 | - | - | |
| 04 | 2.6218: Turn off equipment when not in use | $3,728 | - | - | - | - |
$3,728
-
MMBtu
|
- | |
| 05 | 2.1331: Burn a less expensive grade of fuel | $30,129 | $6,665 | - | - | - | - | $30,129 | |
| TOTAL RECOMMENDED | $50,346 | $26,330 |
$14,675
234,535
kWh
|
$923
-
kW-mo/yr
|
$891 |
$3,728
-
MMBtu
|
$30,129 | ||
| TOTAL IMPLEMENTED | $7,226 | $2,500 |
$2,840
45,390
kWh
|
$469
-
kW-mo/yr
|
$189 |
$3,728
-
MMBtu
|
- | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs