ITAC Assessment: UA0079
ITAC logo
ITAC Assessment: UA0079
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2012
Principal Product Pumps and motors
NAICS 333911: Pump and Pumping Equipment Manufacturing
SIC 3561: Pumps and Pumping Equipment
Sales Range $100
M
to 500
M
# of Employees 550
Plant Area 263,000
ft2
Annual Production 50,000
pieces
Production Hrs. Annual 8,760
hrs
Location (State) Mississippi

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $619,949 14,519,736
kWh
Electricity Demand $121,301 32,769
kW-mo/yr
Electricity Fees $187,100 -
Natural Gas $59,212 7,640
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $72,847 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $3,231

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Increase in Production Savings
01 2.7273: Install desiccant humidity control system $57,749 $240,000 $41,055
961,465
kWh
- $8,273 $(-71,579.0)
-
MMBtu
$80,000
02 2.2437: Recover waste heat from equipment $6,836 $1,500 - - $101 $6,735
-
MMBtu
-
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $5,031 $6,195 $3,743
87,666
kWh
$444
-
kW-mo/yr
$844 - -
04 2.4231: Reduce the pressure of compressed air to the minimum required $3,119 $480 $2,267
53,097
kWh
$329
-
kW-mo/yr
$523 - -
05 2.4221: Install compressor air intakes in coolest locations $112 $106 $83
1,939
kWh
$10
-
kW-mo/yr
$19 - -
TOTAL RECOMMENDED $72,847 $248,281 $47,148
1,104,167
kWh
$783
-
kW-mo/yr
$9,760 $(-64,844.0)
-
MMBtu
$80,000
TOTAL IMPLEMENTED $3,231 $586 $2,350
55,036
kWh
$339
-
kW-mo/yr
$542 - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs