Assessment Year | 2012 |
---|---|
Principal Product | Pumps and motors |
NAICS | 333911: Pump and Pumping Equipment Manufacturing |
SIC | 3561: Pumps and Pumping Equipment |
Sales Range | $100 M to 500M |
# of Employees | 550 |
Plant Area |
263,000
ft2
|
Annual Production | 50,000
pieces
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Mississippi |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $619,949 | 14,519,736 |
kWh
|
$0.043 |
Electricity Demand | $121,301 | 32,769 |
kW-mo/yr
|
$3.70 |
Electricity Fees | $187,100 | - |
|
- |
Natural Gas | $59,212 | 7,640 |
MMBtu
|
$7.75 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $72,847 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $3,231 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Increase in Production Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.7273: Install desiccant humidity control system | $57,749 | $240,000 |
$41,055
961,465
kWh
|
- | $8,273 |
$(-71,579.0)
-
MMBtu
|
$80,000 | |
02 | 2.2437: Recover waste heat from equipment | $6,836 | $1,500 | - | - | $101 |
$6,735
-
MMBtu
|
- | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $5,031 | $6,195 |
$3,743
87,666
kWh
|
$444
-
kW-mo/yr
|
$844 | - | - | |
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $3,119 | $480 |
$2,267
53,097
kWh
|
$329
-
kW-mo/yr
|
$523 | - | - | |
05 | 2.4221: Install compressor air intakes in coolest locations | $112 | $106 |
$83
1,939
kWh
|
$10
-
kW-mo/yr
|
$19 | - | - | |
TOTAL RECOMMENDED | $72,847 | $248,281 |
$47,148
1,104,167
kWh
|
$783
-
kW-mo/yr
|
$9,760 |
$(-64,844.0)
-
MMBtu
|
$80,000 | ||
TOTAL IMPLEMENTED | $3,231 | $586 |
$2,350
55,036
kWh
|
$339
-
kW-mo/yr
|
$542 | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs