Assessment Year | 2011 |
---|---|
Principal Product | Fuel Filters |
NAICS | 333999: All Other Miscellaneous General Purpose Machinery Manufacturing |
SIC | 3569: General Industrial Machinery and Equipment, Not Elsewhere |
Sales Range | $10 M to 50M |
# of Employees | 110 |
Plant Area |
105,000
ft2
|
Annual Production | 450,000
pieces
|
Production Hrs. Annual | 2,100
hrs
|
Location (State) | Alabama |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $72,628 | 1,542,000 |
kWh
|
$0.047 |
Electricity Demand | $53,298 | 5,922 |
kW-mo/yr
|
$9.00 |
Electricity Fees | $22,551 | - |
|
- |
Natural Gas | $35,966 | 4,715 |
MMBtu
|
$7.63 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $18,196 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $1,370 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $13,459 | $24,444 |
$8,531
181,117
kWh
|
$4,410
-
kW-mo/yr
|
$518 | - | - | |
02 | 2.7135: Install occupancy sensors | $668 | $1,241 |
$642
13,637
kWh
|
- | $26 | - | - | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,025 | $800 |
$899
19,086
kWh
|
$1,048
-
kW-mo/yr
|
$78 | - | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $702 | $1,100 |
$375
7,956
kWh
|
$300
-
kW-mo/yr
|
$27 | - | - | |
05 | 2.2437: Recover waste heat from equipment | $832 | $1,935 | - | - | - |
$801
-
MMBtu
|
$31 | |
06 | 2.2223: Enhance sensitivity of temperature control and cutoff | $510 | $1,533 |
$490
10,395
kWh
|
- | $20 | - | - | |
TOTAL RECOMMENDED | $18,196 | $31,053 |
$10,937
232,191
kWh
|
$5,758
-
kW-mo/yr
|
$669 |
$801
-
MMBtu
|
$31 | ||
TOTAL IMPLEMENTED | $1,370 | $2,341 |
$1,017
21,593
kWh
|
$300
-
kW-mo/yr
|
$53 | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs