ITAC Assessment: UA0062
ITAC logo
ITAC Assessment: UA0062
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2011
Principal Product Primary Silicon
NAICS 331110: Iron and Steel Mills and Ferroalloy Manufacturing
SIC 3339: Primary Smelting and Refining of Nonferrous Metals, Except Copper and Aluminum
Sales Range $10
M
to 50
M
# of Employees 102
Plant Area 653,400
ft2
Annual Production 7,300
ton
Production Hrs. Annual 8,760
hrs
Location (State) Alabama

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $12,000,000 300,000,000
kWh
Natural Gas $1,500,000 250,000
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $231,981 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $6,161

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.4231: Reduce the pressure of compressed air to the minimum required $4,392 $60 $4,392
109,799
kWh
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,769 $2,440 $1,769
44,236
kWh
03 2.4133: Use most efficient type of electric motors $225,820 $628,000 $225,820
5,645,400
kWh
TOTAL RECOMMENDED $231,981 $630,500 $231,981
5,799,435
kWh
TOTAL IMPLEMENTED $6,161 $2,500 $6,161
154,035
kWh
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs