| Assessment Year | 2010 |
|---|---|
| Principal Product | Cement |
| NAICS | 327310: Cement Manufacturing |
| SIC | 3241: Cement, Hydraulic |
| Sales Range | less than $500 k |
| # of Employees | 25 |
| Plant Area |
500,000
ft2
|
| Annual Production | 1,500,000
ton
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Alabama |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $8,500,000 | 11,700,000 |
kWh
|
$0.73 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $106,398 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $41,444 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings |
|---|---|---|---|---|---|
| 01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $9,487 | $1,000 |
$9,487
135,528
kWh
|
|
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $29,840 | $10,000 |
$29,840
426,250
kWh
|
|
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,427 | $4,500 |
$3,427
48,960
kWh
|
|
| 04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $7,331 | $640 |
$7,331
104,474
kWh
|
|
| 05 | 2.4323: Use optimum size and capacity equipment | $8,177 | $5,219 |
$8,177
116,813
kWh
|
|
| 06 | 2.4313: Provide proper maintenance of motor driven equipment | $48,136 | $21,075 |
$48,136
687,660
kWh
|
|
| TOTAL RECOMMENDED | $106,398 | $42,434 |
$106,398
1,519,685
kWh
|
||
| TOTAL IMPLEMENTED | $41,444 | $19,719 |
$41,444
592,023
kWh
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs