Assessment Year | 2010 |
---|---|
Principal Product | Cement |
NAICS | 327310: Cement Manufacturing |
SIC | 3241: Cement, Hydraulic |
Sales Range | less than $500 k |
# of Employees | 25 |
Plant Area |
500,000
ft2
|
Annual Production | 1,500,000
ton
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Alabama |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $8,500,000 | 11,700,000 |
kWh
|
$0.73 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $106,398 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $41,444 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings |
---|---|---|---|---|---|
01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $9,487 | $1,000 |
$9,487
135,528
kWh
|
|
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $29,840 | $10,000 |
$29,840
426,250
kWh
|
|
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,427 | $4,500 |
$3,427
48,960
kWh
|
|
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $7,331 | $640 |
$7,331
104,474
kWh
|
|
05 | 2.4323: Use optimum size and capacity equipment | $8,177 | $5,219 |
$8,177
116,813
kWh
|
|
06 | 2.4313: Provide proper maintenance of motor driven equipment | $48,136 | $21,075 |
$48,136
687,660
kWh
|
|
TOTAL RECOMMENDED | $106,398 | $42,434 |
$106,398
1,519,685
kWh
|
||
TOTAL IMPLEMENTED | $41,444 | $19,719 |
$41,444
592,023
kWh
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs