Assessment Year | 2010 |
---|---|
Principal Product | Pipe Coatings |
NAICS | 238320: Painting and Wall Covering Contractors |
SIC | 1721: Painting and Paper Hanging |
Sales Range | $5 M to 10M |
# of Employees | 27 |
Plant Area |
66,700
ft2
|
Annual Production | 2,500
thousand feet
|
Production Hrs. Annual | 2,210
hrs
|
Location (State) | Alabama |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $172,653 | 1,284,850 |
kWh
|
$0.13 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $91,065 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $66,640 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Fees Savings |
---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $19,990 | $39,640 |
$19,990
143,245
kWh
|
- | |
02 | 2.2437: Recover waste heat from equipment | $10,150 | $384 |
$10,150
94,055
kWh
|
- | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $8,870 | - |
$8,870
66,880
kWh
|
- | |
04 | 2.4239: Eliminate or reduce compressed air usage | $1,275 | $2,520 |
$1,275
10,320
kWh
|
- | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $7,170 | $22,560 |
$7,170
56,800
kWh
|
- | |
06 | 2.7134: Use photocell controls | $1,280 | $670 |
$1,280
12,120
kWh
|
- | |
07 | 2.7135: Install occupancy sensors | $1,060 | $935 |
$1,060
9,820
kWh
|
- | |
08 | 2.2515: Use optimum thickness insulation | $13,000 | $13,430 |
$13,000
93,745
kWh
|
- | |
09 | 2.2311: Heat treat parts only to required specifications or standards | $2,800 | $2,000 |
$2,800
16,200
kWh
|
- | |
10 | 2.8112: Combine utility meters | $25,470 | $17,700 | - | $25,470 | |
TOTAL RECOMMENDED | $91,065 | $99,839 |
$65,595
503,185
kWh
|
$25,470 | ||
TOTAL IMPLEMENTED | $66,640 | $83,219 |
$41,170
320,120
kWh
|
$25,470 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Fees Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs