Assessment Year | 2010 |
---|---|
Principal Product | Coatings for Aircraft Part |
NAICS | 332813: Electroplating, Plating, Polishing, Anodizing, and Coloring |
SIC | 7699: Repair Shops and Related Services, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 115 |
Plant Area |
110,000
ft2
|
Annual Production | 25,000
pieces
|
Production Hrs. Annual | 3,120
hrs
|
Location (State) | Alabama |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $521,069 | 6,512,043 |
kWh
|
$0.080 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $30,055 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $6,956 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings |
---|---|---|---|---|---|
01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,495 | - |
$2,495
47,347
kWh
|
|
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,461 | $1,500 |
$4,461
55,754
kWh
|
|
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,885 | $11,676 |
$5,885
73,543
kWh
|
|
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $13,792 | $29,183 |
$13,792
81,463
kWh
|
|
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,016 | $10,675 |
$2,016
25,204
kWh
|
|
06 | 2.7134: Use photocell controls | $352 | $137 |
$352
4,397
kWh
|
|
07 | 2.7135: Install occupancy sensors | $1,054 | $625 |
$1,054
13,175
kWh
|
|
TOTAL RECOMMENDED | $30,055 | $53,796 |
$30,055
300,883
kWh
|
||
TOTAL IMPLEMENTED | $6,956 | $1,500 |
$6,956
103,101
kWh
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs