Assessment Year | 2007 |
---|---|
Principal Product | Flooring |
NAICS | 326199: All Other Plastics Product Manufacturing |
SIC | 3996: Linoleum, Asphalted-Felt-Base, and Other Hard Surface Floor Coverings, Not Elsewhere Classified |
Sales Range | $50 M to 100M |
# of Employees | 225 |
Plant Area |
366,000
ft2
|
Annual Production | 43,000
thousand feet
|
Production Hrs. Annual | 4,000
hrs
|
Location (State) | Alabama |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $451,777 | 12,849,191 |
kWh
|
$0.035 |
Electricity Demand | $567,190 | 50,642 |
kW-mo/yr
|
$11.20 |
Natural Gas | $415,713 | 30,324 |
MMBtu
|
$13.71 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $74,023 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $36,778 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.7134: Use photocell controls | $1,443 | $494 |
$1,443
41,040
kWh
|
- | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $17,268 | $56,213 |
$8,913
253,499
kWh
|
$8,355
-
kW-mo/yr
|
- | |
03 | 2.7135: Install occupancy sensors | $1,149 | $766 |
$383
10,900
kWh
|
$766
-
kW-mo/yr
|
- | |
04 | 2.7135: Install occupancy sensors | $141 | $270 |
$141
4,010
kWh
|
- | - | |
05 | 2.6218: Turn off equipment when not in use | $11,900 | - |
$11,900
341,000
kWh
|
- | - | |
06 | 2.2511: Insulate bare equipment | $1,759 | $309 |
$1,759
50,023
kWh
|
- | - | |
07 | 2.2511: Insulate bare equipment | $1,590 | $153 | - | - |
$1,590
-
MMBtu
|
|
08 | 2.1135: Repair furnaces and oven doors so that they seal efficiently | $23,435 | - | - | - |
$23,435
-
MMBtu
|
|
09 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,816 | $1,400 |
$4,816
136,966
kWh
|
- | - | |
10 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,456 | - |
$2,456
69,847
kWh
|
- | - | |
11 | 2.2614: Use cooling tower or economizer to replace chiller cooling | $2,335 | $7,017 |
$2,335
77,918
kWh
|
- | - | |
12 | 2.2437: Recover waste heat from equipment | $1,979 | $1,979 | - | - |
$1,979
-
MMBtu
|
|
13 | 2.4133: Use most efficient type of electric motors | $717 | $1,940 |
$370
10,536
kWh
|
$347
-
kW-mo/yr
|
- | |
14 | 2.2625: Chill water to the highest temperature possible | $768 | - |
$230
6,528
kWh
|
$538
-
kW-mo/yr
|
- | |
15 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $2,267 | $250 |
$1,171
33,298
kWh
|
$1,096
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $74,023 | $70,791 |
$35,917
1,035,565
kWh
|
$11,102
-
kW-mo/yr
|
$27,004
-
MMBtu
|
||
TOTAL IMPLEMENTED | $36,778 | $494 |
$13,343
382,040
kWh
|
- |
$23,435
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs