| Assessment Year | 2007 |
|---|---|
| Principal Product | Rubber pipe gaskets |
| NAICS | 326220: Rubber and Plastics Hoses and Belting Manufacturing |
| SIC | 3052: Rubber and Plastics Hose and Belting |
| Sales Range | $10 M to 50M |
| # of Employees | 109 |
| Plant Area |
85,000
ft2
|
| Annual Production | 3,500,000
pieces
|
| Production Hrs. Annual | 6,000
hrs
|
| Location (State) | Alabama |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $388,430 | 6,380,128 |
kWh
|
$0.061 |
| Electricity Demand | $12,000 | 15,395 |
kW-mo/yr
|
$0.78 |
| Natural Gas | $366,024 | 32,260 |
MMBtu
|
$11.35 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $113,684 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $46,706 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Water Disposal Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.2511: Insulate bare equipment | $20,117 | $824 |
$20,117
327,214
kWh
|
- | - | |
| 02 | 2.2511: Insulate bare equipment | $34,488 | $1,462 | - |
$34,488
-
MMBtu
|
- | |
| 03 | 2.2135: Repair and eliminate steam leaks | $35,628 | $600 | - |
$35,628
-
MMBtu
|
- | |
| 04 | 3.4155: Meter waste water | $6,725 | - | - | - |
$6,725
-
Tgal
|
|
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,648 | $15,057 |
$5,648
91,866
kWh
|
- | - | |
| 06 | 2.2136: Install / repair insulation on steam lines | $11,078 | $3,916 | - |
$11,078
-
MMBtu
|
- | |
| TOTAL RECOMMENDED | $113,684 | $21,859 |
$25,765
419,080
kWh
|
$81,194
-
MMBtu
|
$6,725
-
Tgal
|
||
| TOTAL IMPLEMENTED | $46,706 | $4,516 | - |
$46,706
-
MMBtu
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Water Disposal Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs