Assessment Year | 1984 |
---|---|
Principal Product | ELECTRIC MOTORS |
NAICS |
n/a
|
SIC | 3621: Motors and Generators |
Sales Range | $5 M to 10M |
# of Employees | 100 |
Plant Area |
n/a
|
Annual Production | 500,000
pieces
|
Production Hrs. Annual | 4,125
hrs
|
Location (State) | Tennessee |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $73,905 | 968,054 |
kWh
|
$0.076 |
Fuel Oil #2 | $17,312 | 2,276 |
MMBtu
|
$7.61 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $8,495 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $2,574 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Fuel Oil #2 Savings |
---|---|---|---|---|---|---|
01 | 2.7212: Install or upgrade insulation on hvac distribution systems | $2,574 | $836 | - |
$2,574
-
MMBtu
|
|
02 | 2.2444: Use hot process fluids to preheat incoming process fluids | $1,363 | $5,000 | - |
$1,363
-
MMBtu
|
|
03 | 2.2511: Insulate bare equipment | $2,851 | $62 |
$2,851
37,515
kWh
|
- | |
04 | 2.2514: Cover open tanks | $727 | $54 | - |
$727
-
MMBtu
|
|
05 | 2.7121: Utilize daylight whenever possible in lieu of artificial light | $980 | $1,550 |
$980
12,896
kWh
|
- | |
TOTAL RECOMMENDED | $8,495 | $7,502 |
$3,831
50,411
kWh
|
$4,664
-
MMBtu
|
||
TOTAL IMPLEMENTED | $2,574 | $836 | - |
$2,574
-
MMBtu
|
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs