| Assessment Year | 2026 |
|---|---|
| Principal Product | Galvanized Steel |
| NAICS | 332812: Metal Coating, Engraving (except Jewelry and Silverware), and Allied Services to Manufacturers |
| SIC | 3479: Coating, Engraving, and Allied Services, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 45 |
| Plant Area |
25,800
ft2
|
| Annual Production | 50,000,000
lb
|
| Production Hrs. Annual | 3,250
hrs
|
| Location (State) | Tennessee |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $48,771 | 595,459 |
kWh
|
$0.082 | |
| Electricity Demand | $37,155 | 2,292 |
kW-mo/yr
|
$16.21 | |
| Electricity Fees | $17,237 | - |
|
- | |
| Natural Gas | $248,543 | 30,033 |
MMBtu
|
$8.28 | |
| Waste Disposal Costs | |||||
| Water Usage | $21,491 | 3,543 |
Tgal
|
$6.07 | |
| Water Disposal | $643 | 58 |
Tgal
|
$11.05 | |
| TOTAL YEARLY COSTS | $373,840 | ||||
| RECOMMENDED SAVINGS* | $115,825 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | - | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Fees Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.2511: Insulate bare equipment | $35,187 | $5,549 | - | - |
$35,187
-
MMBtu
|
- | |
| 02 | 2.8114: Change rate schedules or other changes in utility service | $21,856 | - | - | $21,856 | - | - | |
| 03 | 2.4324: Replace hydraulic / pneumatic equipment with electric equipment | $15,578 | $3,250 |
$15,578
189,975
kWh
|
- | - | - | |
| 04 | 2.8114: Change rate schedules or other changes in utility service | $12,244 | $70 | - | - | - | $12,244 | |
| 05 | 2.2414: Use waste heat from hot flue gases to preheat | $10,677 | $40,000 | - | - |
$10,677
-
MMBtu
|
- | |
| 06 | 2.4239: Eliminate or reduce compressed air usage | $7,404 | $16,000 |
$7,404
90,292
kWh
|
- | - | - | |
| 07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $5,550 | $330 |
$5,550
67,683
kWh
|
- | - | - | |
| 08 | 3.7131: Use a rag recycle service | $1,440 | - | - | - | - | $1,440 | |
| 09 | 2.4239: Eliminate or reduce compressed air usage | $3,528 | - |
$3,528
43,024
kWh
|
- | - | - | |
| 10 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $1,189 | $2,060 |
$1,189
14,500
kWh
|
- | - | - | |
| 11 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $596 | $300 |
$596
7,274
kWh
|
- | - | - | |
| 12 | 2.7135: Install occupancy sensors | $576 | $805 |
$576
7,020
kWh
|
- | - | - | |
| TOTAL RECOMMENDED | $115,825 | $68,364 |
$34,421
419,768
kWh
|
$21,856 |
$45,864
-
MMBtu
|
$13,684 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Fees Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs